Rooppur nuclear plant begins trial power supply to national grid with 350MW
Collected Image
Bangladesh has taken a major step towards nuclear power generation as the first unit of the Rooppur Nuclear Power Plant (RNPP) began supplying 350 megawatts of electricity to the national grid on a trial basis on Tuesday.
The trial supply began at 3:00pm on November 17 under the supervision of Science and Technology Minister Fakir Mahbub Anam, marking a significant milestone in the country's first nuclear power project.
The initial grid connection is part of a series of technical tests to assess the performance of the plant's turbine and generator, ensure operational stability and verify synchronisation with the national grid.
According to the testing schedule, the plant will supply electricity to the grid for around eight to 10 hours during the first phase. Engineers will monitor the equipment's performance, assess system stability and conduct necessary technical evaluations to ensure safe and coordinated grid operations.
After completing the initial trial, the unit will be disconnected temporarily to allow engineers to review operational data. Following a break of approximately 28 hours, it will be reconnected to the grid for another four to six hours of testing.
The successive trial operations will assess the efficiency of the generation system, turbine output and grid synchronisation. Further testing will proceed subject to the results and compliance with safety requirements.
The Bangladesh Atomic Energy Regulatory Authority (BAERA) will have to grant the necessary regulatory approval before the plant can move on to subsequent stages of trial operation.
Commercial operation timeline
Under the agreement with the Russian contractor, the first unit is expected to undergo 10 months of successful trial operation before the Bangladesh Atomic Energy Commission grants Provisional Takeover.
The completion of this process will pave the way for commercial electricity generation at full capacity.
The government will subsequently issue a gazette notification to formally establish Nuclear Power Plant Company Bangladesh Limited (NPCBL) as the plant's operating organisation.
A major addition to national power capacity
The Rooppur facility, located in Ishwardi upazila of Pabna, comprises two units, each designed to generate 1,200MW of electricity. Together, the units will have an installed capacity of 2,400MW.
Once fully operational, the plant is expected to make a significant contribution to meeting the country's growing electricity demand, diversifying its energy mix and strengthening long-term energy security.
The commencement of trial power supply marks a crucial transition from construction and commissioning towards operational readiness, bringing Bangladesh closer to joining the group of countries generating electricity from nuclear energy.