​Tk568cr project unfinished after four years as flyover replaces U-loop plan

Upload Time : 28-11-2026
​Tk568cr project unfinished after four years as flyover replaces U-loop plan Collected Image

 Cumilla Correspondent:
 
A Tk568.93 crore development project aimed at reducing traffic congestion and accidents at Paduar Bazar Bishwaroad in Cumilla remains incomplete even after four years, with only around 37 per cent of the work completed. The project has already missed its deadline, and authorities are now considering changing the original design to build a flyover instead of the planned U-loop, raising fresh questions over its cost, timeline and implementation.
 
Paduar Bazar Bishwaroad is a crucial junction connecting the Dhaka-Chattogram National Highway with the Cumilla-Noakhali regional highway. Thousands of vehicles use the intersection every day. Despite the project's objective of easing traffic congestion and reducing accidents, delays have prevented commuters from receiving the expected benefits.
 
According to the Roads and Highways Department (RHD), the project was approved in 2021 to construct three underpasses along the Cumilla section of the Dhaka-Chattogram National Highway and a U-loop at Paduar Bazar.
 
Titled "Construction of Three Underpasses and Paduar Bazar Intersection U-loop on the Dhaka-Chattogram National Highway", the project was approved at an estimated cost of Tk568.93 crore, with the RHD responsible for its implementation.
 
Under the original plan, a 2,142.70-metre-long U-loop, including ramps, was to be built at Paduar Bazar Bishwaroad. Three underpasses were also planned at Paduar Bazar, the Sadar Dakshin Upazila Gate and the Beltoli Gate of Cumilla University. The underpass at Paduar Bazar was designed to use push-box technology to ensure safe passage for pedestrians.
 
Construction began in October 2022, with completion scheduled for June 2024. However, the deadline passed without the project being completed. Progress stood at around 40 per cent in August 2025, while it is now reported to be approximately 37 per cent, according to relevant sources.
 
Land acquisition complications have emerged as one of the major reasons for the delay. The acquisition of land required for the U-loop on the northern side of the highway has remained unresolved for a long time.
 
Landowners submitted 57 objections over the compensation amounts. According to information published in August 2025, only one of those objections had been settled by then.
 
As a result, construction progressed on one side of the project while work on the other side could not begin. Around 40 per cent of the U-loop construction on the Dhaka-bound side had been completed, but land acquisition on the Chattogram-bound side remained pending.
 
Relevant officials said the remaining work could be completed within a year if the required land were handed over.
 
Former Cumilla Deputy Commissioner Md Amirul Kaisar had said that the old U-turn at Paduar Bazar had been temporarily closed to prevent accidents. He also said efforts would be made to resolve all 57 land acquisition objections within three months.
 
Current Deputy Commissioner Roji Akter said discussions were underway with the Ministry of Road Transport and Bridges to expedite the project.
 
Meanwhile, as the project remained stalled for an extended period, authorities initiated moves to revise its design. According to relevant sources, although the original plan included a U-loop, construction of a flyover is now being considered under the proposed revised design.
 
Md Adnan Ibn Hasan, sub-divisional engineer at the RHD's Cumilla office, said a new design was being prepared to prevent accidents caused by the risky U-turn at Paduar Bazar Bishwaroad.
 
He expressed hope that implementation of the revised design would make traffic movement along the highway safer and smoother.
 
With the U-loop construction still incomplete, vehicles continue to use the risky U-turn at Paduar Bazar Bishwaroad. Vehicles travelling from the Dhaka-Chattogram Highway towards the Cumilla-Noakhali road, and those coming from the opposite direction, have to turn across the highway, creating the risk of collisions with fast-moving traffic.
 
The issue drew renewed attention in 2025 after four members of the same family were killed when their private car was crushed under a lorry at Paduar Bazar. Following the accident, the old U-turn was closed and traffic was diverted through alternative routes to reduce the risk of further accidents.
 
Earlier, Additional Superintendent of Police of Cumilla Region Kirtiman Chakma and Superintendent of Police Md Khairul had said that unplanned U-turns on the highway should be closed and U-loops constructed quickly to improve road safety in the area.
 
Paduar Bazar Bishwaroad is not only one of the main entry points to Cumilla city but also an important transport junction for vehicles travelling to and from several southeastern districts, including Noakhali, Lakshmipur, Chandpur and Feni. Congestion at the intersection therefore affects traffic on surrounding roads as well.
 
Once completed, the project is expected to improve traffic movement on the Dhaka-Chattogram Highway and the Cumilla-Chandpur regional highway. It was also intended to provide safer crossing facilities for pedestrians. However, prolonged delays have prevented commuters from receiving these benefits.
 
Local BNP leader Mahbubur Rahman said around 80 per cent of the project could have been completed if land acquisition had been carried out on time. In his view, completing the land acquisition process quickly could have allowed the remaining construction work to be finished within a few months.
 
The Tk568.93 crore project now faces fresh uncertainty due to land acquisition complications, prolonged delays and the proposed design change. With only a limited portion of the work completed after four years, questions have emerged over the project's implementation and effectiveness. It remains uncertain when the revised design will be finalised and when construction will resume and be completed.